25 August 2022 Mount Abu 2.5m Telescope: first light and performance assessment
Author Affiliations +
Abstract
AMOS has recently completed the on-site erection and performance evaluation campaign of the 2.5m telescope that is installed on Mount Abu (India) for the Physical Research Laboratory. The 20-m-focal-length telescope has a Ritchey-Chrétien optical configuration. It is equipped with a primary active mirror; an active positioning of the secondary mirror and a first order adaptive optical system. It operates in the 0.37-4 μm spectral range. The project fulfillment relies on the AMOS multidisciplinary expertise in design; manufacturing and verification of high-accuracy optical; mechanical and opto-mechanical systems. This paper presents the assembly; integration; alignment and verifications carried out on site. The alignment relies on the coma-free point method. The end-to-end telescope performances (image quality; pointing; tracking) are measured on sky using the verification instrument in combination with wavefront-curvature sensing and lucky imaging techniques.
Conference Presentation
© (2022) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
Christian Bastin, Gregory P. Lousberg, Olivier Pirnay, Cédric Adam, Pierre Albart, Jonathan De Ville, Alexis Feutry, Carlo Flebus, Nicolas Fontana, Eric Gabriel, Audrey A. Lanotte, Fabien Lemagne, Thibault Leseur, Laurence Méant, Nathalie Ninane, Sabrina Orban, Jean-Marc Tortolani, and Jonathan Verspecht "Mount Abu 2.5m Telescope: first light and performance assessment", Proc. SPIE 12187, Modeling, Systems Engineering, and Project Management for Astronomy X, 121870H (25 August 2022); https://doi.org/10.1117/12.2632285
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
Telescopes

Active optics

Mirrors

Optical alignment

Image quality

Optics manufacturing

Cameras

RELATED CONTENT

OAJ 2.6m survey telescope optical alignment and on sky...
Proceedings of SPIE (August 09 2016)
Mt ABU 2.5m Telescope: design and fabrication
Proceedings of SPIE (July 06 2018)
DAG 4m telescope: assembly, integration and testing
Proceedings of SPIE (July 06 2018)
Active Optics From The Test Set Up To The...
Proceedings of SPIE (September 20 1989)
The Magellan Telescopes: a performance update
Proceedings of SPIE (August 04 2010)

Back to Top