9 August 2010 Mixing completion, commissioning, and operations at the LBT
Richard F. Green, John M. Hill, Joar Brynnel, James H. Slagle, David S. Ashby, Norman J. Cushing, John K. Little, R. Mark Wagner, Marco Pedani
Author Affiliations +
Abstract
By June 2010, the Large Binocular Telescope Observatory will have supported six semesters of observing with prime focus imaging, with the addition of IR imaging and spectroscopy in the most recent. Interspersed in the last year were installation and commissioning of one direct and one bent Gregorian focal station and extended commissioning of the first bent Gregorian focal station. We examine the lost time statistics and distribution of issues that reduced on-sky access in the context of the limited technical support provided for observing. We also note some of the restrictions imposed by the alternation of engineering and commissioning activities with scheduled observing time. The goal is to apply the lessons learned to the continuing period of observation plus commissioning anticipated as new spectroscopic, adaptive optics, and interferometric capabilities are added through 2012.
© (2010) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
Richard F. Green, John M. Hill, Joar Brynnel, James H. Slagle, David S. Ashby, Norman J. Cushing, John K. Little, R. Mark Wagner, and Marco Pedani "Mixing completion, commissioning, and operations at the LBT", Proc. SPIE 7737, Observatory Operations: Strategies, Processes, and Systems III, 773706 (9 August 2010); https://doi.org/10.1117/12.856812
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
Telescopes

Observatories

Cameras

Adaptive optics

Spectrographs

Camera shutters

Interferometers

RELATED CONTENT

Scientific planning for the VLT and VLTI
Proceedings of SPIE (July 27 2016)
LBTO's long march to full operation: step 2
Proceedings of SPIE (August 01 2016)
Overview of the Subaru telescope instrumentation
Proceedings of SPIE (March 07 2003)
Mixing completion, commissioning, and operations at the LBT
Proceedings of SPIE (September 13 2012)
Results from a portable adaptive optics system on the 1...
Proceedings of SPIE (February 21 2003)
Science with IMACS on Magellan
Proceedings of SPIE (February 13 2003)

Back to Top